Monday, April 7, 2008

Work Method Statement for Ceiling Work

WORKS METHOD STATEMENT

CEILING WORKS

TABLE OF CONTENTS


1.0 WORK ORGANISATION
2.0 DESIGN CONSTRAINTS AND COORDINATION
3.0 CONTRACTING METHODS
4.0 PROCUREMENT METHODS
5.0 RESOURCE PROVISIONS
6.0 LOGISTICS PROVISIONS
7.0 MATERIAL MANAGEMENT SYSTEMS
8.0 CONSTRUCTION METHODS AND TECHNOLOGY
9.0 CONSTRUCTION PHASING AND WORKFLOW
10.0 TRAFFIC MANAGEMENT AND MONITORING
11.0 SAFETY PROGRAMME
12.0 QUALITY ASSURANCE AND CONTROL PROGRAMMES
13.0 INDUSTRIAL RELATIONS POLICIES
14.0 ENVIRONMENTAL MONITORING PROGRAMMES
15.0 APPENDICES


1.0 INTRODUCTION

This Work Method Statement covers the ceiling work activities and the preparation, application and workmanship shall comply with the standard and specification. The types of ceiling are as below :

1. Plasterboard ceiling
2. Suspended aluminium clip in plank ceiling
3. Exposed grid ceiling (MFT)


2.0 DESIGN CONSTRAINTS AND COORDINATION

Not Applicable.


3.0 CONTRACTING METHODS

The Conditions of Contract have been reviewed by PCSB and particularly those conditions in respect of Sub-contractors. The conditions are bespoke for this project and therefore be required to be reflected in any form of Sub-contract utilized on the project.

Please refer to PHOS-CN-010 to PHOS-CN-030 for the Contract Procedures.


4.0 PROCUREMENT METHODS

Since PCSB is liable for the performance of any Sub-contractor, it is vital that only companies with proven track records in the relevant activity will be engaged as Sub-contractors.

It is acknowledge that before any part of the works can be sublet, the approval of the Employer’s Representative is required.

Please refer to PHOS-PR-010 to PHOS-PR-030 for the procurement procedures.
5.0 RESOURCE PROVISIONS

5.1 Manpower/Labour

The number of manpower/labour to be used during the earthworks activities have been identified in the Manpower Record.




5.2 Plant Equipment /Tools

• Ramset concrete nailer
• Makita concrete driller
• Laser Level machine
• Plumbs
• Basic hand tools
• Makita steel bench cutters
• Ceiling gun
• Ladder
• Steel square ruler
• Drilling Machine


6.0 LOGISTICS PROVISIONS

The logistic control shall be in accordance with the approved Site Logistic Plan.

7.0 MATERIAL MANAGEMENT SYSTEMS

Please refer to PHOS-CP-040 for the Material Control Procedure.

8.0 CONSTRUCTION METHODS AND TECHNOLOGY

8.1 Plasterboard Ceiling

• All leveling set out coordinates shall be based on the setting out levels provided on site by Main Contractor.
• Once the setting out dimensions are determined, the coordinator shall proceed to identify areas of M&E services that requires additional adjustments. Once completed, the coordinator shall inform the subcontractor on the request for an inspection by coordinator and clerk of work approval prior to commencing of any physical works.
• Then installation of the ceiling brackets and hanger rods. Upon completion of the droppers and hangers, then proceed to install the adjustable suspension brackets prior to installing the main top cross rail and TCR to FCR connector and lastly the furring channels.
• On completion of the above, the Coordinator Head Foreman shall inspect the framing for any defective or inferior works and shall make all necessary remedial instruction so as to ensure levelness and a secure and rigid framing has been installed.
• Once all ceiling are completed, the subcontractor shall request that the trades commence all marking and setting out works so as to enable all opening or penetration be made prior to plastering works.






8.2 Suspended Aluminium Clip in Plank Ceiling

• Clip in section installation should follow strictly to the shop drawing as approved.
• Confirm the ceiling finish marking and fix wall angle to perimeter wall at the correct height and check for level.
• Fix suspension wire with suspension brackets attached, to approximated height at 1000mm (recommended from the manufacturer) maximum centre in both directions.
• Tight up the primary clip in section with suspension wire, adjust height of primary clip in section to a line stretched between wall angles and ensuring the fitting correctly tightness.
• Install the secondary clip in section 1200mm centre and check all fitting for tightness and safety.
• After suspension components are installed, all the M&E opening marking as per drawing, the subcontractor will provide the ceiling panels / plank as required for M&E trade to do the opening and installation by M&E respective contractor.
• The Subcontractor will complete up the remaining ceiling panel/plank after all the M&E works is completed, corrected and agreed upon in writing. Installation of the ceiling panel/plank (600mm x 1200mm) are simply insert to the help in level position and then applying pressure on the dimple point.

8.3 Exposed Grid Ceiling (MFT)

• Plan the ceiling layout to provide even margins at the perimeter (grid space for ceiling panels at each end of the ceiling is the same).
• Centre the ceiling both ways to ensure centre lines are at right angles to each other and main runners are at right angles to purlins or joists.
• Fix wall angle trim to perimeter walls at the correct height of the ceiling and check that they are level. Mitre the wall angle trim (shadow line) around piers and columns.
• Fix suspension rod brackets to structural framing or concrete soffit to appropriate height at 1200mm maximum centers in each direction.
• Attach suspension rods (with suspension hangers attached) to suspension rod brackets previously fastened to supporting members, with rod end bent down into a hook.
• Attach the main runners to suspension hanger ensuring the hanger hook is firmly threaded through the top of the main runner.
• Adjust the suspension hanger or rod threaded to set the height of the main runners to a level line between the wall and wall angle trims.
• Insert cross tee runners intersecting main runners at 600mm centres.
• After suspension components are installed, fix light fittings, air register and blind boxes. Check all fittings for tightness and safety and insert ceiling tiles.





9.0 CONSTRUCTION PHASING AND WORKFLOW

Not applicable.

10.0 TRAFFIC MANAGEMENT AND MONITORING

The Logistic Manager and the traffic management contractor shall be responsible for the management and control of the traffic in and out from the construction site.

11.0 SAFETY PROGRAMME

Please refer to PHOS-HS-010 Health and Safety Plan.

12.0 QUALITY ASSURANCE AND CONTROL PROGRAMMES

The Engineer has to ensure that works are being done according to the specifications to achieve best quality.

13.0 INDUSTRIAL RELATIONS POLICIES

Not Applicable

14.0 ENVIRONMENTAL MONITORING PROGRAMMES

Please refer to PHOS-EMP-001 Environmental Management Plan

15.0 APPENDICES

15.1 Plasterboard ceiling checklist
15.2 Suspended aluminium clip in plank ceiling checklist
15.3 Exposed grid ceiling (MFT) checklist
15.4 Inspection and test plan
15.5 Job Safety Analysis

No comments: